College of Admission Tests Multan

Work and Rate Problems

Solve the question of and select the option from the choices A through D/E. Check your Answer and view the explanation.

Question: 9

4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?
  • 30 days
  • 40 days
  • 50 days
  • 60 days

  Show/Hide Explanation 

Correct Answer: B

None

Let 1 man's 1 day work = x

and 1 woman's 1 days work = y.

Then, 4x + 6y = 1/8

and 3x+7y = 1/10

solving, we get y = 1/400 [means work done by a woman in 1 day]

10 women 1 day work = 10/400 = 1/40

10 women will finish the work in 40 days