Work and Rate Problems

Solve the question of and select the option from the choices A through D/E. Check your Answer and view the explanation.

Question: 2

To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take
  • 24 days
  • 16 days
  • 12 days
  • 8 days

  Show/Hide Explanation 

Correct Answer: D

None
A+B 1 day work = 1/8 B+C 1 day work = 1/12 A+B+C 1 day work = 1/6 We can get A work by (A+B+C)-(B+C) And C by (A+B+C)-(A+B) So A 1 day work = capture -39589796