Work and Rate Problems

Solve the question of Work and Rate Problems and select the option from the choices A through D/E. Check your Answer and view the explanation.

Question: 1

A can do a job in 16 days, B can do same job in 12 days. With the help of C they did the job in 4 days. C alone can do the same job in how many days ?
  • op a -88933320
  • op b -36291952
  • op c -48177728
  • op d -44084692

  Show/Hide Explanation 

Correct Answer: D

None
In this question we having, A's work, B's work and A+B+C work. We need to calculate C's work. We can do it by, (A+B+C)'s work - (A's work + B's work). Let's solve it now: C's 1 day work = exp -14654896